82nd Street Promised Labor & Materials
Bathroom Fixtures - August 2021
- Donald Libby quoted and collected material & labor costs of $4,623.00
- No materials were delivered.
- No labor was performed.
- Second Bathroom Shower fixture materials cost $941.32
- Second Bathroom Toilet and Sink fixture materials cost $200.79
- Second Bathroom Sink fixture materials cost $323.58
- Master Bathroom Shower fixture materials cost $328.28
- Additional materials cost was $6,020.70
- Completion additional materials cost was $7,486.00
Air Conditioner Labor & Materials - December 2024
- Donald Libby quoted and collected material & labor costs of $6,000.00
- No materials were delivered.
- No labor was performed.
- Completed additional materials & labor cost was $6,437.00
Window Replacement Labor & Materials - August 2021
- Donald Libby quoted and collected material & labor costs of $1,722.
- No materials were delivered.
- No labor was performed.
- Completed additional materials & labor cost was $13,356.
Door Replacement Labor & Materials - March 2023
- Donald Libby quoted and collected material & labor costs of $1,719.
- No materials were delivered.
- No labor was performed.
- Completed materials cost was $3,260.
- Completed labor cost was $1,650.
- Completed additional cost was $3,191.
Pocket Doors - Interior, August 2021
- Donald Libby quoted and collected material & labor costs of $465.00.
- No materials were delivered.
- No labor was performed.
- Hardware materials cost was $467.20.
- Hardware installation cost was $1200.00.
- Door materials cost was $320.00.
- Labor cost was $500.00.
- Completed additional cost was $2,022.
Tile Floors, August 2021
- Donald Libby texted and said that he could get a 32% discount on material costs making the total $17,909.29.
- He did not get a discount and the true material costs were $26,176.33.
- Donald Libby, on March 3, 2022, said that he would present a cashiers check to Durango Stone to cover the balance of payments for the tile.
- He did not show up and make any payment.
- $7,676.32 is was paid by Jim to Durango Stone.
- Completed additional cost was $8,266.
Skylights Replacement Labor & Materials - August 2021
- Donald Libby quoted and collected material & labor costs of $1,760.00
- No materials were delivered.
- No labor was performed.
- Replacement materials & labor cost was $3,520.00
- Completed additional cost was $1,760.
Outside Stone Bathtub - September 2021
- Donald Libby quoted and collected material & labor costs of $2,900.00
- No materials were delivered.
- No labor was performed.
- Replacement materials cost was $9,5030.76.
- Replacement labor cost estimate was $1,200.
- Completed additional cost was $7,804.
Ceiling Fans - September 2021
- Donald Libby quoted and collected material & labor costs of $2,190.00
- No materials were delivered.
- No labor was performed.
- Replacement materials cost was $3,040.00.
- Completed additional cost was $850.
Outdoor Shower and Tub Fixtures - September 2021
- Donald Libby quoted and collected material & labor costs of $2,168.00
- No materials were delivered.
- No labor was performed.
- Replacement tub faucet materials cost was $2,118.00.
- Replacement shower faucet materials cost was $452.60.
- Completed additional cost was $408.
Insulation- August 2021
- Donald Libby quoted and collected material & labor costs of $4,069.
- Inferior/Fake materials were delivered and installed.
- Correct (Havelock) materials cost was $23,940.
- Correct product additional cost was $19,871.